Bespoke Spraybooth Installation for Penske Porsche, Germany
A challenging first-floor installation for Penske Porsche in Germany, featuring a fully electric Cyclone spraybooth designed around a low ceiling and complex existing services.
This project involved the delivery of a fully bespoke spraybooth facility for an automotive client as part of their expansion into a new region. The new site was developed to support increased operational capacity, providing a purpose-built workshop designed around both flexibility and performance.
Delivered as a complete turnkey project, STL managed the design, manufacture, and installation of the facility, ensuring a seamless process from concept through to completion.
The installation formed part of an ongoing multi-site relationship, supporting the customer’s continued growth and wider market presence.
The project required a fully customised solution to fit within an existing workshop space, while meeting the demands of a modern automotive refinishing operation.
In addition to spatial constraints, the installation needed to deliver high levels of performance in terms of airflow, lighting, and heating, all while complying with relevant industry regulations. A tight delivery programme added further complexity, requiring careful planning and coordination to ensure the project could be completed on time without compromising quality.
We delivered a complete turnkey solution, taking responsibility for all aspects of the project from initial design through to final installation.
The system included:
In addition to the spraybooth systems, STL designed and constructed supporting internal spaces, including offices, a kitchen, breakout area, and plant room, all built using composite panelling to create a clean, cohesive finish throughout the facility.
Despite a demanding four-week programme, the project was delivered on time and to specification.
The completed facility provides a modern, efficient environment for automotive refinishing, supporting the customer’s expansion into a new region. The flexible layout and high-performance systems enable reliable day-to-day operation, while the overall finish reflects a professional standard aligned with the customer’s brand.
This project forms part of a wider partnership, with us continuing to support the customer across multiple sites as they grow their presence.